BRIEF-Alexco's bellekeno silver mine project on schedule

May 10 (Reuters) - Alexco Resource Corp: * Alexco's bellekeno silver mine project on schedule for third quarter commissioning and production * Mine development, including underground mine services and surface infrastructure, is about 45 percent complete * Says mill construction about 30 percent complete * Says overall project remains on schedule and on budget for completion and commissioning in Q3 of calendar 2010 * Total actual construction and development capital to achieve production is currently forecasted at C$41.96 million * Says current mine plan will have three stopes operational in Q3 and two more operational in Q4 ((Bangalore Equities Newsroom; +91 80 4135 5800; within U.S. +1 646 223 8780)) (For more news, please click here) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved.